Finding snags is easy. Keeping track of them until they are fixed is the hard part. Here is the snag list we recommend, free to download.

Every construction site has snags: a cracked tile, a door that won't close, a socket in the wrong place, a patch of plaster that needs redoing. On their own they are small. Together, at handover, they decide whether the client signs off happily or starts holding back payment.

The problem is rarely finding snags. It is keeping track of them until they are actually fixed. This is the snag list format we recommend, free to download.

Download the snag list template (PDF) One page, 20 rows. Print it for the snag walk or fill it in digitally.

What a snag list is

A snag list (also called a punch list) is a running record of defects and unfinished items on a construction site: what is wrong, where it is, who has to fix it and whether it is done. It starts long before handover. The best sites log snags from the first floor up, so the list at the end is short.

The columns every snag list needs

1. Number

A simple running number (S-001, S-002). It sounds trivial, but "S-047 is still open" is a sentence everyone understands. "That crack near the stairs" is not.

2. Location

Block, floor, room, wall: as exact as you can make it. "Block B, level 2, flat 4, bathroom, east wall" lets a tradesman walk straight to it.

3. Description

What is wrong, in plain words: "Grout missing around basin, 30 cm." Not "fix bathroom."

4. Trade or responsible party

Who has to fix it: the tiler, the electrician, the main contractor, a named subcontractor. A snag with no owner does not get fixed.

5. Photo

One dated photo when the snag is raised, and ideally one when it is closed. Before-and-after photos end most arguments about whether something was really fixed.

6. Date raised and target date

When it was found and when it should be done. The gap between the two is the number your client cares about.

7. Status and date closed

Open, in progress, fixed, or verified closed, with the date and the person who checked it. "Fixed" (the trade says so) and "closed" (someone checked) are not the same thing.

How to run a snag walk

Why snags get lost in the site WhatsApp group

On most construction sites, snags are raised the fastest way possible: a photo in the site WhatsApp group with "pls fix." It works for about a day. Then the photo scrolls away under deliveries, attendance and good mornings. Nobody can say how many snags are open, which ones are overdue, or whether the one from three weeks ago was ever done.

The fix is not to stop using WhatsApp, because the crew won't. It is to get every snag out of the chat and onto a list with an owner, a date and a status. Our WhatsApp for construction playbook covers how to run the group itself so less gets lost.

The honest footnote: keeping the list up to date

A snag list on paper or a spreadsheet only works if someone copies every snag out of the chat, every day. That is the step that gets skipped.

SiteTab is a WhatsApp contact you add to your construction site group. When someone posts a snag photo, it files it as an issue with the date, the location if it was mentioned and a link to the original message, and keeps it open, with the days counting, until someone says it is fixed. You see every open snag on your phone or laptop without scrolling the chat. One group is $10 a month, with a 7-day free trial and nothing to install.